EDITOR'S PAGE
TI's crown jewel
Just off the LBJ Expressway in Dallas lies what will soon be the crown
jewel of Texas Instruments' production facilitiesDMOS 6. Originally
built in 1996 as a 200-mm fab but mothballed when demand turned south,
the once-empty shell is quickly filling up with equipment and support
systems as teams of engineers and technicians ramp the facility for 300-mm
production. During a late-March trip to Texas, I toured the fab and spoke
with some key personnel bringing DMOS 6 on-line.
The largest fab in the company's family, DMOS 6's main cleanroom
area sprawls 118,000 sq ft over the freestanding waffle slab, with another
32,000 sq ft of adjacent clean manufacturing area for CMP, wafer recycling,
pod services, and the like. A familiar golden-orange rectangular glow
delineates the lithography area in the center of the huge production floor,
which is about as large as two football fields. Not surprisingly, the
proportions of the equipment match the scale of the room itselffrom
miniwarehouse-like implanters, to windowed wet benches reminiscent of
streetcars, to a prodigious cluster tool called by one engineer "an Endura
on steroids."
DMOS 6 will be a fully automated, computer-integrated manufacturing
(CIM) facility. Every wafer will be tracked on the CIM system, with the
overhead transport system carrying color-coded wafer pods (green for nonmetal,
red for metal, amber for copper) to and from the prodigious stockers and
the various process and metrology cells. Because minienvironment technology
is used, the main cleanroom operates at Class 100 and features a layout
strikingly different from traditional ballroom fabsthere are no
bays and chases. Besides opening up the workspace, the scheme has other
obvious benefits: the tools' subsystems and components are readily accessible
for fine-tuning or maintenance.
Since the fab was in the engineering phase during my visit, most of
the wafers were still transferred manually, but the one operational litho
clustera rambling, 36-ft-long scanner/track combowas benefiting
from the first deliveries of the automated materials handling system.
When the fab reaches production levels, the peripatetic robots will carry
a hell of a lot of silicon: the final capacity could reach 35,000+ wafer
starts per week (a whopping 78,000+ in 200-mm equivalent wafers, if you
use the 2.25x ratio).
Greg Winterton, DMOS 6's engineering manager, was part of the
original 200-mm project group and has worked on the 300-mm project core
team for more than 18 months. "We started receiving tools last September,
and we continue to receive and install tools. [More than 180 tools had
been received by late March.] We started silicon in mid-February, and
we got transistors out and they look pretty good. The transistors match
nearly to our mother fab [the Kilby Fab, or K-Fab] and to the spec. We'll
have yielding devices out of here in the next month or so."
TI's plan is to qualify the 0.18-µm aluminum interconnect
module this September, quickly followed by the 0.13-µm copper process
in December, according to Winterton. "We're starting up on our proven
high-yielding aluminum interconnect process. The process is running in
four other factories and the technology is well understood. So if I bring
it in here, I can see what squeaks and rattles in the process flow and
I can be guaranteed that it's not some marginality with new technologyit's
an issue with our integration of the tool set.
"There's been a couple of minor integration issues going to 300
mm. We do have a full tool set in place for processing but many are one-of-a-kind
tools, so we're suffering some when a tool goes down for a couple of days.
But the results I've gotten so far on 300 mm closely match what I've seen
on 200 mm.... You plan for the worst, you hope for the best, and it's
actually been more toward the better: all the things I feared really haven't
happened. Things like CMP on 300 mmit's actually better than 200
mm."
A veteran engineer who has seen his share of fab follies, Winterton
nonetheless seems cautiously optimistic about the DMOS 6 ramp. "It's been
easier than I thought it would be thus far. That's not to say there isn't
some land mine out there, but we haven't stepped on it yet."
Tom Cheyney
Editor
tom.cheyney@cancom.com

MicroHome |
Search | Current Issue | MicroArchives
Buyers Guide | Media Kit
Questions/comments about MICRO Magazine? E-mail us at cheynman@gmail.com.
© 2007 Tom Cheyney
All rights reserved.
|