Facilities Technologies
Using a database to support an equipment hookup project
Frank Mattukat and Stephan Migge, M+W Zander
The use of a single, equipment cardbased database can facilitate
process tool installation and provide as-built documentation for later
fab buildout.
In any new fab construction project, hookupthe connection of all process
and support equipment to the building's facility systemsis the last step
before the start-up of production. A complex and time-consuming process,
hookup involves a variety of systems, ranging from electrical supplies
and gas distribution lines to drains and mechanical exhaust systems. The
hookup project described in this article was carried out at the Advanced
Micro Devices (AMD) Fab 30 in Dresden, Germany (shown in Figure
1). As the general contractor, M+W Zander (Stuttgart, Germany) designed
and built this turnkey fab, which includes approximately 12,000 m2
of Class 100T cleanroom space and was designed for the production of the
Athlon processor, a highly sophisticated PC cpu with six metal layers.
The entire project was budget driven, yet at the same time the fab had
to be built to accommodate future chip generations and further decreases
in device geometry.
 |
| Figure 1: AMD Fab 30 in Dresden, Germany. |
 |
| Figure 2: Schematic representation of a typical hookup project.
|
To support the hookup project team, M+W Zander developed customized
database and software tools for use in the design and document control
of all process toolrelated connection activities. Based on equipment
cards, this database system is the focus of this article. Special emphasis
is given to the use of value engineering to minimize costs without adversely
affecting the performance of the production equipment.
Project Overview
Although the main activities and processes of a hookup project partly
overlap, as shown in Figure 2, such projects typically involve six steps:
- Fact-findingsetup of the design team and schedule, preparation
of the database and tender (bidding) documents, and preauditing of subcontractors.
- Designschematic design of all typical component assemblies
and process equipment. Detailed design activities include generating
plan views of all tools on all levels, space management guidelines and
drawings, and vacuum pump rack and foundation drawings. All the tool-related
design documents are combined in the equipment cards, which are available
to the client and subcontractors. The release target of each equipment
card is 4 weeks ahead of the tool's scheduled dock date (delivery at
the fab), so that as much of the piping and cabling as possible can
be preinstalled to minimize the time between the delivery and start-up
qualification of the tool. Additional schematic design information can
be issued before the completion of the equipment card in order to procure
materials that have long lead times.
- Construction managementsite setup and all construction activities,
including environmental, health, and safety considerations; quality
assurance/quality control; rigging of equipment; clean protocols; and
controlling, reporting, and scheduling.
- Installation.
- Commissioning and closeoutfollowing the installation of connections
to the equipment, the facility systems have to be turned on and the
tools validated and commissioned.
- Handoverfollowing commissioning, the tools are handed over
to production for use and the hookup facility systems and piping are
handed over to the fab's facility department.
The project's main activities can be further broken down into a series
of interrelated detailed tasks. Figure 3 provides an example of such tasks
and their interactions. From design to handover, however, all activities
have to be scheduled and coordinated on a tool-by-tool basis, which is
a complex and demanding process. In some projects, some tools may still
be in the design stage after others have already been handed over.
 |
| Figure 3: Fact-finding process flow diagram. (Fac Hut = facilities
hookup team and CM = construction management.) |
The hookup project described here started design in January 1998, and
between May and November approximately 350 process and production support
systems were installed. Of those, approximately 60 were major toolsetchers,
CVD machines, and wet benches, some of which have as many as 20 individual
support modules (such as remote frames and vacuum pumps). The remainder
of the toolset consisted of production support equipment such as metrology
equipment, CMP systems, and equipment used for maintenance purposes. Installation
manpower was well above 250 during peak times, not including management
and indirect labor. Most of the installation phase was conducted as a
single-shift operation, since local labor laws restrict round-the-clock
installation programming. The typical peak-time installation rate was
five major tools (complex production equipment) and five minor tools (e.g.,
metrology tools) per week.
The Equipment Card
With the customized database system, an equipment card for each process
tool is generated during fact-finding and used throughout the entire life
cycle of the hookup project. The equipment card is the data-entry platform
of the database, which provides basic document control for all equipment-related
hookup activities. It also provides as-built documentation for use in
power generation plant consumption analyses, the optimization of facility
system mains and submains, and the utilization of supply piping. Furthermore,
it provides background documentation for the design of similar tools when
a fab extends its production capacity. Because equipment card data can
be output via Microsoft Excel, information can be easily e-mailed to tool
vendors for quick review and updating.
Each process tool's equipment card reflects the exact tool configuration
along with the exact location of all parts with regard to building levels
and coordinates, as seen on the sample wet bench equipment card in Figure
4. Main frame and support equipment are listed and detailed, along with
weights, dimensions, and the contact persons for that particular tool.
 |
| Figure 4: Sample equipment card for a wet bench. |
The equipment card also lists every facility system connection to the
process tool along with all necessary related information, including any
interconnects integral to the process equipment. The sample equipment
card in Figure 5, for example, includes bulk-gas consumption data. It
also identifies the fab facility takeoff valve and the exact connection
type that is used for each gas hookup, and indicates whether a shutoff
valve, pressure regulator, or filter is required in the hookup installation.
This information verifies that the related procurement activities have
been properly documented and allows the contractor to review them with
the fab owner to avoid either redundant or missing components, such as
local UPS support modules.
 |
|
Figure 5: Sample equipment card listing the bulk gases
that are supplied to a wet bench.
|
Each equipment card is divided into nine main facility system groups:
bulk gases, chemicals, drains, electrical, exhaust, liquids, monitoring,
pump vacuum, and specialty gases. This division follows well-established
practices in assigning subcontractor responsibilities and reflects the
reality that each facility system group has its own key components (for
example, filters and pressure regulators are required for gas systems,
but not for electrical supplies or drains). Rather than using standardized
configurations for each facility type, the hookup team individually checks
which key components are needed in each particular process tool connection,
thereby minimizing installed components while meeting specifications.
Dividing the equipment card into system groups also aids unit-cost analysis,
simplifies contractor material remeasure, and helps specify the scope
of a given subcontractor's work.
In addition to their use during the design phase of the Fab 30 hookup
project (as described below), equipment cards were used to support the
commissioning of the facility systems. Exhaust systems, for example, were
adjusted by the commissioning team according to the maximum consumption
values on the equipment cards, which were gathered and discussed during
fact-finding. Because all the data were available in a single standardized
format instead of on various vendor drawings, the team was able to complete
its tasks expeditiously. To keep the content up-to-date, feedback generated
during commissioning and start-up was entered into the database and identified
with revision notation.
When the average consumption is known, the equipment database can be
used to determine facility main and submain loading and to predict possible
shortfalls for future buildout. An up-to-date database that contains all
known service consumption values is an effective tool for determining
medium- and long-term investment timelines for future service extensions.
In the described project, data for the complete fab buildout are being
added.
Design Document Generation
During the schematic design phase of the hookup project, data from the
equipment cards were used with other parts of the database to automatically
create schematic drawings and their associated parts lists. Using data
from a single source minimized CAD and engineering manpower requirements
while enhancing the data integrity of all design documents. Data from
the equipment cards provided tool- specific connection requirements, and
the database also provided information on pipe and cable sizing as well
as on typical connection details. Both types of information had been discussed
and agreed on earlier by the hookup project team.
The automatically generated schematic design documents consisted of
piping and installation diagrams (see the example in Figure 6) and parts
lists denoting all main components (see Figure 7). The diagrams showed
all piping and components used for the hookup of a particular tool and
were divided into the nine main facility groups to facilitate the identification
of scope specifications and encourage "apples-to-apples" bidding processes.
 |
| Figure 6: Detail from a piping and installation diagram showing
bulk gas lines to a wet bench. |
 |
| Figure 7: Parts list for the diagram in Figure 6. |
The autogeneration of design documents is a key element of the hookup
database and offers the following advantages:
- Rapid design production.
- Savings in CAD and engineering manpower.
- Automatic generation of bills of materials and remeasure sheets
in conjunction with the generation of piping and installation diagrams.
- Automatic sizing of hookup pipes and cables according to agreed-on
design rules.
- Standardization of drawing symbols.
- Full data integrity between equipment cards and schematic designs.
Cost Control and Change Management
Because chip manufacturers are constantly under pressure to minimize
costs, cost control and change management are key factors in every fab
construction project. Therefore, the current project was executed on a
unit-price basisthat is, every installed component was assigned a fixed
price in the negotiations with all subcontractors. This price was divided
into material and labor components to enhance pricing transparency and
to make bidding more competitive.
Budgeting was done on a tool-by-tool and facility-by-facility basis.
Every piece of process equipment had its own budget, which included a
section for each facility (mainly corresponding to the nine main facility
system groups). The initial overall budget was based on benchmark figures
and was then refined by factoring in the actual cost of the first tools
handed over. During the course of the project, budgets were updated using
the database, the bills of materials, and the unit prices. After completion
of each tool, the actual cost was fed back into the budget to update the
cash-flow forecast.
Supervisors tallied the amounts of piping and components that were installed
immediately after installation, and the results were noted on a remeasure
sheet. The template for these sheets is based on the piping and installation
drawings and is generated automatically during the autogeneration of the
diagrams. All field modifications that had a cost impact were subject
to approval from AMD prior to execution. The approval was logged into
the database along with a budget estimate of the change.
Project Results and Outlook
In all major construction projects, the main goals include staying on
schedule and below budget. To achieve the latter goal, it is essential
that hookup cost relative to equipment capital cost (EQC) be minimized
by utilizing efficient design and construction management methods, supported
by a database system. Figure 8 indicates the success of the current project
in that regard. Specifically, the figure shows the trend of hookup cost
relative to EQC over several past projects and the Fab 30 project, along
with a future target.
 |
| Figure 8: Trend in hookup cost versus equipment capital cost
achieved by the design-and-build contractor. |
Figure 9 shows the number of tools handed over for production use during
the project's 15-week installation period. The lower line depicts the
same data for a project completed several years ago. Comparing the two
lines reveals that more tools were handed over more rapidly in the current
project. As these two figures suggest, the hookup project managed to satisfy
the owner in regard to both cost and schedule.
 |
| Figure 9: Number of tools handed over during the installation
period of two projects. |
An additional result of using the integrated database system is that
as-built documentation has been provided to the client in an electronic
format for future use. Besides the electronic source files, all equipment
cards, system specifications, and test reports have been converted into
Adobe Acrobat .pdf files, which do not require an expensive CAD installation.
M+W Zander will continue to support AMD by installing tools for capacity
extensions and new process areas until the end of this year. These efforts
include copper metallization tools for future Athlon processors. The current
project team consists of members from both companies, who cooperate to
ensure a smooth step-by-step handover of tools for production use. In
addition, the database developed for this project is scheduled to become
the standard for all of M+W Zander's future hookup activities.
Conclusion
The connections between process equipment and a newly built fab's facilities
(the so-called hookup) is the last step before starting up production.
In AMD's Fab 30, a database system designed and customized by the general
contractor was used to support the hookup project team from initial fact-finding
to the handover of the completed installations. By collecting tool-related
information on equipment cards and using a single database for design
and construction management support, the team completed this project in
a timely and cost-efficient manner. The project approach was influenced
by considerations of value engineering, close control of design documentation,
installation coordination, and change management.
Acknowledgments
The authors would like to thank all of the hookup team members, especially
facility manager Hans Lüdeck and Werner Freimann, the AMD hookup
manager. They also wish to thank Danny Hoenig of Kent Technical Application.
Frank Mattukat joined M+W Zander (Stuttgart, Germany) in 1996
and was involved with the AMD Fab 30 hookup project from the initial presentation.
He was project manager for phases II and III of the hookup. He has a degree
in mechanical engineering from the University of Stuttgart, Germany. (Mattukat
can be reached at +49 7032 943215 or frank.mattukat@mngrafix.com.)
Stephan Migge is a department manager at M+W Zander, where he
is responsible for the management and control of major projects. Since
joining the company in 1986, he has been a project manager involved in
the engineering, design, construction, coordination, and scheduling of
process supply facilities. He received a degree in mechanical engineering
from the Fachhochschule Esslingen in 1982. (Migge can be reached at +49
711 88041314 or stephan.migge@mw-zander.com.)

MicroHome |
Search | Current Issue | MicroArchives
Buyers Guide | Media Kit
Questions/comments about MICRO Magazine? E-mail us at cheynman@gmail.com.
© 2007 Tom Cheyney
All rights reserved.
|